REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS


BOARD MEETING DATE:  September  13, 2022
CATEGORY:  Consent - Public Works-20.

SUBJECT:

Approve and authorize the Public Works Director to sign a Notice of Completion for the “Shasta County Jail Door Replacement and Modification Project,” Contract No. 610534, and record it within 15 days of actual completion.

DEPARTMENT: Public Works
Sheriff-Jail

Supervisorial District No. :  All

DEPARTMENT CONTACT:  Al Cathey, Public Works Director, (530) 225-5661

STAFF REPORT APPROVED BY:  Al Cathey, Public Works Director

Vote Required?

Simple Majority Vote
General Fund Impact?

No General Fund Impact 

RECOMMENDATION

Approve and authorize the Public Works Director to sign a Notice of Completion for the “Shasta County Jail Door Replacement and Modification Project,” Contract No. 610534, and record it within 15 days of actual completion.

DISCUSSION

On June 29, 2021, CML Security, LLC was awarded the contract for construction on the Jail Door Replacement and Modification Project. The project in general consists of supplying, installing, and modifying new and existing security doors, locks and other door accessories.  The work is nearly complete.

ALTERNATIVES

The Board may decline to authorize the filing of a Notice of Completion.  The lien period would extend for 90 days instead of 30 days.  Final payment to the contractor would be delayed by 60 days.

OTHER AGENCY INVOLVEMENT

The Recommendation has been reviewed by the County Administrative Office.

FISCAL IMPACT

The total estimated cost of the project is $1,900,000. Sufficient appropriations were included in the Adopted Fiscal Year 2020-21, 2021-22 and 2022-23 Land Buildings & Improvements budgets for the project.  Accumulated Capital Outlay funded the project.