| | | | | | | | REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS
BOARD MEETING DATE: September 13, 2022 CATEGORY: Consent - Public Works-17.
SUBJECT:
Approve and authorize the Public Works Director to sign a Notice of Completion for the “Cascade Office Building Storm Drain Repair Project,” Contract No. 610947, and record it within 15 days of actual completion. |
| | | | | | | | Supervisorial District No. : All
DEPARTMENT CONTACT: Al Cathey, Public Works Director, (530) 225-5661
STAFF REPORT APPROVED BY: Al Cathey, Public Works Director
Vote Required?
Simple Majority Vote | General Fund Impact?
No General Fund Impact |
|
| | | | | | | | RECOMMENDATION
Approve and authorize the Public Works Director to sign a Notice of Completion for the “Cascade Office Building Storm Drain Repair Project,” Contract No. 610947, and record it within 15 days of actual completion. |
| | | | | | | | DISCUSSION
On July 26, 2022, Sunrise Excavating was awarded the contract for construction on the Cascade Office Building Storm Drain Repair project. The project in general consists of replacing approximately 1,060 feet of storm drainpipe from the Cascade Office Building parking lot to Oregon Gulch. The work is nearly complete. |
| | | | | | | | ALTERNATIVES
The Board may decline to authorize the filing of a Notice of Completion. The lien period would extend for 90 days instead of 30 days. Final payment to the contractor would be delayed by 60 days. |
| | | | | | | | OTHER AGENCY INVOLVEMENT
The Recommendation has been reviewed by the County Administrative Office. |
| | | | | | | | FISCAL IMPACT
The total cost of the project is estimated to be $500,000. Adequate appropriations have been included in the Adopted Fiscal Year 2022-23 Land, Buildings & Improvements budget. Social Services fund balance will cover the project cost. |
|