Item Coversheet

REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS


BOARD MEETING DATE:  November  1, 2016
CATEGORY:  Consent - Public Works-10.

SUBJECT:

Adult Probation Building Roofing Project - Notice of Completion

DEPARTMENT: Public Works

Supervisorial District No. :  All

DEPARTMENT CONTACT:  Pat Minturn, Public Works Director, (530) 225-5661

STAFF REPORT APPROVED BY:  Pat Minturn, Public Works Director

Vote Required?

Simple Majority Vote
General Fund Impact?

No Additional General Fund Impact 
RECOMMENDATION

Approve and authorize the Public Works Director to sign a Notice of Completion for the “Adult Probation Building Roofing Project,” Contract No. 610434, and record it within 15 days of actual completion of the work.

SUMMARY

The Adult Probation Building has a new roof and three new HVAC package units.

DISCUSSION

The Adult Probation Building (1626 Court Street) had some roof leaks.  On August 23, 2016, the Board awarded the Adult Probation Building Roofing Project to Wait Roofing and Seamless Gutter, Inc. A new roof was installed with a 20-year manufacturer’s warranty on labor and materials.  Several package HVAC units had to be removed to install the new roof so they were replaced as well.

ALTERNATIVES

The Board may decline to file a Notice of Completion. The lien period would extend for 90 days instead of 30 days. Final payment to the contractor would be delayed by 60 days.

OTHER AGENCY INVOLVEMENT

The recommendation has been reviewed by the County Administrative Office.

FINANCING

The total cost of this project, including design, construction, inspection and contingencies, is estimated to be $120,000.  Adequate funds have been included in the Adopted 2016/17 LB&I budget.  There is no additional General Fund impact.