| | | | | | | | REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS
BOARD MEETING DATE: September 11, 2018 CATEGORY: Consent - Public Works-19.
SUBJECT:
West Central Landfill Gas Monitoring Probes – Notice of Completion
|
| | | | | | | | Supervisorial District No. : 2
DEPARTMENT CONTACT: Pat Minturn, Public Works Director, (530) 225-5661
STAFF REPORT APPROVED BY: Pat Minturn, Public Works Director
Vote Required?
Simple Majority Vote | General Fund Impact?
No General Fund Impact |
|
| | | | | | | | RECOMMENDATION
Approve and authorize the Public Works Director to sign a Notice of Completion for the “West Central Landfill Gas Monitoring Probes,” Contract No. 207512, and record it within 15 days of actual completion of the work. |
| | | | | | | | SUMMARY
Five methane monitoring probes have been installed at West Central Landfill. |
| | | | | | | | DISCUSSION
On June 5, 2018, ABC Liovin Drilling, Inc. was awarded the West Central Landfill Gas Monitoring Probes project. Five more methane monitoring probes were installed around the waste cells. This work is nearing completion. |
| | | | | | | | ALTERNATIVES
The Board may decline to file a Notice of Completion. The lien period would extend for 90 days instead of 30 days. Final payment to the contractor would be delayed 60 days. |
| | | | | | | | OTHER AGENCY INVOLVEMENT
The County Administrative Office has reviewed the recommendation. |
| | | | | | | | FINANCING
The total cost of this project is estimated to be $67,820. Adequate funds have been included in the Adopted 2018/2019 Solid Waste budget. There is no General Fund impact. |
|