| | | | | | | | REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS
BOARD MEETING DATE: July 17, 2018 CATEGORY: Consent - Public Works-19.
SUBJECT:
Public Defender Roofing Project – Notice of Completion
|
| | | | | | | | Supervisorial District No. : All
DEPARTMENT CONTACT: Pat Minturn, Public Works Director, (530) 225-5661
STAFF REPORT APPROVED BY: Pat Minturn, Public Works Director
Vote Required?
Simple Majority Vote | General Fund Impact?
No Additional General Fund Impact |
|
| | | | | | | | RECOMMENDATION
Approve and authorize the Public Works Director to sign a Notice of Completion for the “Public Defender/Adult Probation Roofing Project,” Contract No. 610435, and record it within 15 days of actual completion of the work. |
| | | | | | | | SUMMARY
The Public Defender/Adult Probation Building Roofing Project is complete. |
| | | | | | | | DISCUSSION
Roof leaks have plagued the Public Defender/Adult Probation Building. Limited repairs were unsuccessful. A project was proposed to remove the old roof, repair dry rot and install a 60 mil PVC Single-Ply Membrane System with a 20-year warranty. On February 6, 2018, the Board awarded the construction contract to MCM Roofing Company, Inc. The work is estimated to be completed on July 13, 2018. |
| | | | | | | | ALTERNATIVES
The Board may decline to file a Notice of Completion. The lien period would extend for 90 days instead of 30 days. Final payment to the contractor would be delayed by 60 days. |
| | | | | | | | OTHER AGENCY INVOLVEMENT
The County Administrative Office has reviewed this recommendation. |
| | | | | | | | FINANCING
The total cost of this project, including engineering and contingencies, is estimated to be $374,000. Adequate funds were included in the Adopted 2018/19 LB&I budget. There is no additional General Fund impact. |
|