REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS


BOARD MEETING DATE:  May  22, 2018
CATEGORY:  Consent - Public Works-9.

SUBJECT:

StreetSaver Software

DEPARTMENT: Public Works

Supervisorial District No. :  All

DEPARTMENT CONTACT:  Pat Minturn, Public Works Director, (530) 225-5661

STAFF REPORT APPROVED BY:  Pat Minturn, Public Works Director

Vote Required?

Simple Majority Vote
General Fund Impact?

No General Fund Impact 

RECOMMENDATION

Take the following actions regarding the “2017 Pavement Management System,” Contract No. 701604: (1) Approve and authorize the Public Works Director to enter into an agreement with the Metropolitan Transportation Commission in the amount of $10,680 to provide technical support for database setup and first-year subscription of the StreetSaver software; (2) authorize the Public Works Director, or his/her designee, to accept the StreetSaver standard End User License Agreement; and (3) authorize the Public Works Director, or his/her designee, to renew the StreetSaver software subscription annually in an amount not to exceed $5,000 per year.

SUMMARY

A software agreement with Metropolitan Transportation Commission (MTC) is proposed to manage the County’s pavement inventory.

DISCUSSION

Road pavements are a major County asset and expense.  On September 12, 2017, the County entered into an agreement with Nichols Consulting Engineers, Chtd. (NCE) for a County-wide Pavement Management System (PMS).  The product characterizes pavement condition and provides design guidance. NCE has evaluated the County road network and set up the PMS database.  A StreetSaver software subscription with MTC will be required for continued use.

ALTERNATIVES

The Board may decline to enter into the proposed agreement. StreetSaver software is essential to the PMS.

OTHER AGENCY INVOLVEMENT

County Counsel has approved the agreement as to form. Risk Management and Information Technology have reviewed and approved the agreement. The County Administrative Office has reviewed this recommendation.

FINANCING

Adequate funds to implement the PMS have been included in the Proposed 2018/19 Roads budget. There is no General Fund impact.

ATTACHMENTS:
DescriptionUpload DateDescription
StreetSaver Technical Support Services Agreement5/9/2018StreetSaver Technical Support Services Agreement
StreetSaver End User License Agreement5/9/2018StreetSaver End User License Agreement