| | | | | | | | REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS
BOARD MEETING DATE: September 19, 2017 CATEGORY: Consent - Public Works-14.
SUBJECT:
Olinda Road Widening Cycle 5 Project – Right of Way |
| | | | | | | | Supervisorial District No. : 2
DEPARTMENT CONTACT: Pat Minturn, Public Works Director, (530) 225-5661
STAFF REPORT APPROVED BY: Pat Minturn, Public Works Director
Vote Required?
Simple Majority Vote | General Fund Impact?
No General Fund Impact |
|
| | | | | | | | RECOMMENDATION
Take the following actions regarding the "Olinda Road Widening Cycle 5 Project," Contract No. 702977: (1) Approve and authorize the Chairman to sign right-of-way contracts with: (a) Joshua Murphy and Brittany Murphy for right-of-way (0.10 acres at $600) plus a Federal Highway Administration (FHWA) signing incentive of $1,000; and (b) Sandra Suzuki and Annett Nielson for right-of-way (0.20 acres at $1,000) plus an FHWA signing incentive of $1,000; and (2) accept two Easement Deeds conveying the right-of-way parcels. |
| | | | | | | | SUMMARY
Right-of-way acquisition is proposed to widen Olinda Road. |
| | | | | | | | DISCUSSION
The County is preparing to construct paved shoulders along two miles of Olinda Road from Green Leaf Lane to Sammy Lane. The project is funded through the Federal Highway Safety Improvement Program (HSIP). The project will require right-of-way acquisition from 14 property owners. Local agencies may offer a bonus to property owners who sign in a timely manner. The incentives must be offered equally to all property owners and are reimbursable by FHWA. Agreements have been reached with twelve owners within the requisite sixty days of accepting the first written offer. Negotiations continue with the two remaining corporate owners. |
| | | | | | | | ALTERNATIVES
The Board may decline to acquire the right-of-way. The acquisitions are necessary to construct the project. |
| | | | | | | | OTHER AGENCY INVOLVEMENT
Caltrans oversees the project funding. County Counsel has approved the contracts as to form. Risk Management has reviewed and approved the contracts. The recommendation has been reviewed by the County Administrative Office. |
| | | | | | | | FINANCING
The total project cost estimate is $1,500,000. Federal funds will cover 90%. Adequate funds are included in the Adopted FY 2017/18 Roads budget. There is no General Fund impact. |
|