| | | | | | | | REPORT TO SHASTA COUNTY BOARD OF SUPERVISORS
BOARD MEETING DATE: June 27, 2017 CATEGORY: Consent - Public Works-28.
SUBJECT:
Public Works – Resource Management Expansion Budget Amendment
|
| | | | | | | | DEPARTMENT: | Public Works Resource Management
|
|
| | | | | | | | Supervisorial District No. : All
DEPARTMENT CONTACT: Pat Minturn, Public Works Director, (530) 225-5661
STAFF REPORT APPROVED BY: Pat Minturn, Public Works Director & Richard W. Simon, Director of Resource Management
Vote Required?
4/5 Vote | General Fund Impact?
General Fund Impact |
|
| | | | | | | | RECOMMENDATION
Take the following actions: (1) Approve a budget amendment increasing appropriations and revenue by $150,000 within the Fiscal Year (FY) 2017-18 Lands, Buildings and Improvements budget for the "Resource Management Expansion Project;" and (2) approve a budget amendment increasing appropriations by $173,980 within the FY 2017-18 Resource Management budget for the "Resource Management Expansion Project" to be offset by use of unassigned fund balance. |
| | | | | | | | SUMMARY
A budget amendment is proposed to complete the Resource Management Expansion Project and purchase furniture. |
| | | | | | | | DISCUSSION
On May 9, 2017, the Board awarded the Resource Management Expansion project to Walker Construction. Construction has commenced. Costs of $150,000 will be incurred in FY 17/18 to complete the project. These expenditures need to be included in the FY 17/18 LB&I budget. The total project budget remains at $206,600.
Additional appropriations of $23,980 are requested in the Resource Management budget for the purchase of furnishings and equipment for the expansion. |
| | | | | | | | ALTERNATIVES
The Board may decline to approve the budget amendment. Currently budgeted appropriations in the FY 17/18 LB&I budget will be insufficient to pay the contractor. |
| | | | | | | | OTHER AGENCY INVOLVEMENT
Resource Management supports this recommendation. The County Administrative Office have reviewed this recommendation. |
| | | | | | | | FINANCING
Total estimated cost for the Resource Management Expansion project remains unchanged at $206,600. There is General Fund impact with the Resource Management Expansion project. |
|